Benchmarking Topics:
- Typical contractor fees for cost plus fee with GMP construction manager/general contractor projects of various sizes
- Whether or not to reimburse for general liability insurance or have it covered by Fee
- Typical charges for general liability insurance
- Typical charges for Subcontractor Default Insurance (subguard)
- Typical charges for Contractor Controlled Insurance Programs (CCIP)
- Typical charges for worker's compensation when the contractor is self-insured and/or uses high deductibles
- Change order markup percentages allowed on subcontractor self-performed work and work performed by sub-subcontractors
- Actual wire and conduit costs versus published "book prices"
Course Outline:
Introduction to Effective Auditing of Construction Activity
- Audit objectives related to controlling construction costs
- Project team roles and responsibilities
- Delivery systems - fast track, design build, conventional
- Contract procurement methods, types, and phases
Cost Plus and Time and Material Contracts - Typical Overcharges
- Design contract billings for time and reimbursables
- Billings for personal computer and/or mainframe computer time
- Construction contractor and/or construction manager billings for labor and labor burden
- Billings for contractor-owned equipment, third-party equipment rental, expendable tools, equipment and consumables, and material used during construction
- Transactions dealing with subcontractors
Auditing Construction Change Orders
- Typical overcharges in lump sum change orders
- Electrical change order - discussion exercise
- Change order labor and labor burden pricing
Auditing Lump Sum or Unit Price Contracts
- Quality and scope of work overcharges
- Substitution of materials or methods
- Not performing required services
- Not installing proper quantities
- Special types of lump sum contract overcharge situations
- Adjusting allowances
- Required bonds and insurance
- Improper charges for sales tax
- Special unit price overcharge situations
- Excessive quantities billed
- Improper measurement method used
- Inaccurate measurements
- Billings for excessive quantities actually performed
Program Fee: $1,195 per person
EARLY REGISTRATION DISCOUNT: $1,095 per person if registered by August 27, 2010.
Registration FEE is payable to:
Construction Audit & Cost Control Institute, Inc.
3941 Legacy Drive, Suite 204 #218A, Plano, TX 75023.
Registration FEE may be paid by check, MasterCard, Visa or American Express.
Program fee includes instruction, all program materials, lunch each day and refreshment breaks
Register:
Register On-Line: Click here to register on-line
Register by Fax or Mail: Click here to download printable registration form.
Register by Telephone: Call Lynn Runyon at Courtenay Thompson & Associates (214) 361-8346
Program Schedule:
Tuesday: 8:30 am - 4:30 pm
Wednesday: 8:30 am - 4:30 pm
Cancellation and Refund:
Enrollment is limited to assure maximum opportunity for participation and exchange of ideas. Substitutes will be accepted until the program starts. Cancellations will be accepted up to 14 calendar days prior to program start without incurring a $95 late cancellation fee. Full fee is charged for failure to attend when enrollment has not been cancelled as specified. Contact Lynn Runyon at Courtenay Thompson & Associates, 214-361-8346 or lynn@ctassoc.com.
CPE
All participants are eligible to receive up to 16 Continuing Professional Education credits (CPE's) to fulfill professional accreditation requirements. Field of Study: Auditing. Course Level: Basic. Group-live, lecture-style seminar; no prerequisites or advance preparation required. For information regarding CPE, complaint or program cancellation, please contact Courtenay Thompson & Associates at 214-361-8346.
Courtenay Thompson & Associates is registered with the National Association of State Boards of Accountancy (NASBA), as a sponsor of continuing professional education on the National Registry of CPE Sponsors. State boards of accountancy have final authority on the acceptance of individual courses for CPE credit. Complaints regarding registered sponsors may be addressed to the National Registry of CPE Sponsors, 150 Fourth Avenue North, Suite 700, Nashville, TN 37219-2417. Web site: www.nasba.org
Hotel Reservations:
We have blocked a limited number of upgraded rooms at Farfield Inn & Suites, by Marriott (The Colony, Texas) that will be available at $85 per night for the evenings of 10-4-2010 and 10-5-2010.
Click here to reserve your hotel room:
Construction Audit King Rooms
Construction Audit Queen/Queen Rooms
Or you may call Marriott's reservations at 1-800-MARRIOTT. Ask for the "Construction Audit and Cost Control" Rate of $85.
Venue:
The seminar classes will be held at the Cascades Event Center at The Colony (a suburb of Dallas). The Cascades Event Center is attached to the Fairfield Inn & Suites:
5909 Stone Creek Drive
Hwy 121 & Spring Creek Pkwy
The Colony, TX 75056
Seminar Developers:
R. L. Townsend & Associates, Inc. and Courtenay Thompson & Associates have jointly developed our professional development training seminars related to construction cost control and audit.